Crews have been plugging away on phase two. The new storm drain trunk line from Olive Street to Main Street has been completed as well as the excavation between Olive Street and Main Street on the west half of S. 8th Avenue. Crews have started hauling subbase gravel through this section as well. Excavation on the East half of S. 8th between Olive Street and Main Street should begin toward the end of this week/first of next week. By the end of next week we anticipate having the excavation completed and plan to continue hauling subbase gravel and base gravels with curb and gutter and concrete flatwork to follow.