Monday, July 9, 2012

Paving was completed on Friday, July 6th between Harrison Street and Koch Street. Crews have since finished the colored concrete crosswalks and Thermoplastic pavement markings will begin on Tuesday, July 10th. It appears that phase one of the project will be re-opened to traffic between Harrison Street and Story Street on Monday, July 16th.