Wednesday, September 5, 2012

The main portion of curb and gutter throughout phase 2 was completed last week. This week crews are working on topsoiling and placing/finishing road base gravels. Next week the concrete crews will be back to finish up the curb and gutter and begin pouring the remaining approaches and pedstrian ramps throughout phase 2. We currently anticipate paving to begin around September 19th/20th with project completion around the first of October.